Project in Dubai

Objective: 

To construct and deliver an office to the client, ensuring the highest standards of quality and the safety of the office staff.

Project in Dubai

Year: 2024
Size: 21,052 sqft
Location: Dubai, UAE
Design by: Jouzy
Built by: Xworks Interiors LLC
Project Management by: Xworks Interiors LLC

Challenges:

Material Approval – The initially selected material exceeded both the project timeline and the client’s budget.
Project Duration – The original duration requested for the construction project was 90 days. However, during the tender submission and job award process, the timeline was reduced to 60 days, and by the time work began on site, it was further shortened to 45 days. Despite this, the project was completed in 60 days.
Working Hours – Given that 90% of the building is occupied by tenants, the contractor was instructed to work only during nighttime hours. Even non-noisy tasks were not permitted during the day shift.

Solutions:

The materials were selected with consideration for value engineering (VE) options, and all choices were made in coordination with the client and consultant.
Due to the shortened timeline and limited working hours, the number of manpower and staff on the project had to be increased

What our Clients
say About us.

Are You Ready To Get Started ?

Get in touch with us today, and we'll collaborate to create a stunning workspace that exceeds your expectations.

    Get in Touch

    We are always ready to help and answer any questions you might have. Write to us and we’ll get back to you as quickly as possible.